One delay, three methods, three apportionments
A small project, ten delay events, 11 days of actual delay. Depending on the method, the Employer's share ranges from 6 to 9 days.
The project comprises a garage and its access road. Contract completion is day 40; actual completion is day 51. Ten delay events occur: six at the Employer's risk, four at the Contractor's. Each method is run step by step: the programme is rebuilt at every step and the activities that change are outlined.
- Activity (planned or as-built)
- Activity on the critical path
- Forecast remaining duration
- Baseline programme, for reference
- Employer delay (excusable and compensable)
- Contractor delay (non-excusable)
- Activity changed at the current step
- Data date and window under analysis
- Contract completion (day 40)
- Planned and calculated completion, with the difference
As-planned vs as-built
The baseline programme is compared with the as-built programme. Each party's delays are summed and concurrency is dealt with by offsetting, without any critical path analysis.
- Starting point: the baseline programme. Completion on day 40.
- The as-built programme: completion on day 51, 11 days late. The ten delay events are shown on the bars.
- Contractor delays: 3 + 1 + 5 + 3 = 12 days.
- Employer delays: 7 + 1 + 4 + 2 + 4 + 3 = 21 days.
- Assumed concurrency: the smaller of the two sums, 12 days. Net Employer share: 21 − 12 = 9 days.
- The balance falls to the Contractor: 11 − 9 = 2 days. Result: 9 days to the Employer, 2 days to the Contractor, with no review of the critical path.
- Employer
- 9 d
- Contractor
- 2 d
- Total apportioned
- 11 d
- Actual delay
- 11 d
Windows analysis
The programme is updated with actual progress on days 10, 21, 32, 40 and 51, and the remaining work is rescheduled from each data date. Within each window, the movement in the completion date is attributed to the events on that period's critical path.
- Starting point: the baseline programme. Completion on day 40, critical path through the garage.
- Window 1, updated on day 10. Event 1 (labour problem) is critical: completion on day 41, slippage 1 day, attributed to the Contractor.
- Window 2, updated on day 21. Event 3 (brick supplier) is critical: completion on day 42, slippage 1 day, attributed to the Contractor.
- Window 3, updated on day 32. Event 6 (extra window) is critical: completion on day 44, slippage 2 days, attributed to the Employer.
- Window 4, updated on day 40. The critical path moves to the access road: completion on day 49, slippage 5 days, of which 2 to the Contractor and 3 to the Employer.
- Window 5, completion of the works on day 51: slippage 2 days, attributed to the Employer.
- Result: 7 days to the Employer, 4 days to the Contractor, 11 days in total, matching the actual delay. Each day of slippage is tied to the period and the critical path in which it arose.
- Employer
- 7 d
- Contractor
- 4 d
- Total apportioned
- 11 d
- Actual delay
- 11 d
Impacted as-planned
Delay events are added to the baseline programme one at a time, in the order they occurred. After each addition the critical path is recalculated, and the movement in the completion date is attributed to the party responsible for that event.
- Starting point: the baseline programme. Completion on day 40, critical path through the garage.
- Event 1, Contractor, 3 days: labour problem. It is critical: completion moves to day 43, impact 3 days.
- Event 2, Employer, 7 days: unforeseen adverse ground while excavating the access road. The access road has float: completion unchanged, impact 0 days. The baseline finish-to-start (FS) link is kept (circle): the method does not reproduce the optimisation achieved on site, FS-3d, where the next task started 3 days before this one finished.
- Event 3, Contractor, 1 day: the Contractor's brick supplier is late. Completion on day 44, impact 1 day.
- Event 4, Employer, 1 day: thicker floor slab, decided on the Contractor's advice. Off the critical path: impact 0 days.
- Event 5, Employer, 4 days: works suspended while the Employer decides on the suitability of the hardcore. The access road becomes critical: completion on day 45, impact 1 day.
- Event 6, Employer, 2 days: extra window ordered after the brickwork was finished. The garage is critical again: completion on day 46, impact 1 day.
- Event 7, Contractor, 5 days: poorly constructed sections reworked after a quality control test. The access road is critical again: completion on day 50, impact 4 days.
- Event 8, Employer, 4 days: Employer-furnished equipment not available in time. Completion on day 54, impact 4 days.
- Events 9 and 10, 3 days each: the Contractor's low productivity, door type changed by the Employer. Off the critical path: impact 0 days.
- Result: 6 days to the Employer, 8 days to the Contractor, 14 days in total against 11 days of actual delay. The method keeps the planned logic and disregards how the works actually progressed.
- Employer
- 6 d
- Contractor
- 8 d
- Total apportioned
- 14 d
- Actual delay
- 11 d
Three apportionments for the same project
| Method | Employer | Contractor | Total apportioned |
|---|---|---|---|
| As-planned vs as-built | 9 d | 2 d | 11 d |
| Windows analysis | 7 d | 4 d | 11 d |
| Impacted as-planned | 6 d | 8 d | 14 d |
The actual delay is 11 days in every case. What changes is how it is apportioned. The choice of method depends on the contract, the programmes available and their reliability, and should be justified in the report.
Data adapted from N. Braimah, “Construction Delay Analysis Techniques — A Review of Application Issues and Improvement Needs”, Buildings, 2013, 3(3), 506-531, licensed under CC BY 3.0. Illustrative example. Updates on days 10, 21, 32, 40 and 51, as stated in the article text.
Exercise: a dam programme
A dam construction programme tracked over seven versions (T0 and six updates): dates, durations, float, critical path, logic links and milestones compared from one version to the next, with indicators useful for delay analysis and practical cases.